Project Summary
The HUB for Human Impact
La Jolla Country Day School - HUB for Human Impact
22,160
Square Feet
3
Stories
2026
Completion Year
Active
Closeout Status

Project Description

The HUB for Human Impact is a 22,160 square foot, three-story building designed to benefit students of every age by fostering innovation, collaboration, and real-world problem solving. The building serves as a campus destination where students, faculty, and community partners can engage in interdisciplinary learning and mission-driven initiatives. The human-centered learning commons will benefit students of every age by fostering innovation, collaboration, and real-world problem-solving. The Hub boldly empowers Torreys to connect their knowledge to their impact.

Project Location

Project Facts

Building Area 22,160 SF
Stories 3
Location 9490 Genesee Avenue
Project Type New Construction
Occupancy Classification Educational Facility
Photovolataic System Yes

Project Team

Owner La Jolla Country Day School
Architect domus Studio
General Contractor Dempsey Construction
Project Manager Kevin Worth
Assistant Project Manager Dan Wagner
Assistant Project Manager Nathan Mau

Closeout Status

As-Built Drawings Complete
RFIs Complete
Submittals Complete
O&M Manuals Active
Warranties Pending

Key Milestones

Contracted Start May 19, 2025
Contracted Finish September 28, 2026
Substantial Completion September 18, 2026
Construction Budget Under Budget
Construction Schedule Ahead of Schedule

Construction Phase

Planning and Design Complete
Pre-Construction and Procurement Complete
Construction Complete
Punch Active
Closeout Active
 

Project Completion Status

97%
Project Complete
 

Punch List Status